Concrete bridge with a red cycle path crossing a canal on an overcast day
Projects

Infrastructure

Stadshaven Bridge

A concrete road and cycle bridge across the harbour canal, with separated cycle lanes and low-maintenance piers.

Completed
2008
Investment
€24 million
Location
Zwolle
Length
180 m
Sector
Infrastructure
Scope
Design & Build

Project overview

Construction time

18 months

A 180-metre road and cycle bridge across the harbour canal, designed and built by one integrated team. Prefabricated deck sections kept the waterway open to shipping for most of the works.

Our approach

Deck sections were cast off site, floated in by barge and lifted into place during a handful of planned weekend closures. Cyclists and boats kept moving for almost the entire build.

Highlights

  1. 01Separated cycle lanes in both directions
  2. 02Prefabricated concrete deck sections
  3. 03Low-maintenance piers designed for 100 years
Next projectAurora Kantoorcentrum