How VELDIN projects are planned, coordinated and delivered, from the first challenge to the final outcome.

01 · Project Stories19 August 2026

Coordinating structure before work reaches site

How the Kadezicht Kantoren team resolved structural and installation clashes in the model, months before the first floor was poured.

Kadezicht Kantoren, a canal-side office building in Amsterdam with a brick and glass facade.
Location
Amsterdam
Sector
Offices & Workplaces
Completed
2001
View project
  1. 01Challenge

    A canal-side office with long spans, dense building services and a tight site. Late changes to structure or ducts would have meant demolition work in a building with almost no room to store or move materials.

  2. 02Planning

    Structure, facade and installations were modelled together from the start of the technical design. Openings in floors and beams were agreed before the structural drawings were released for production.

  3. 03Coordination

    Weekly clash sessions brought the structural engineer, installers and our engineers around one model. Every issue had an owner and a deadline, and nothing went to site until it was resolved.

  4. 04Delivery

    Precast elements arrived with openings already in place. Site teams worked from the same coordinated model, so installation followed the structure without cutting or rework.

  5. 05Outcome

    The frame was completed without structural changes on site, and the installation teams could start directly behind the structure. The project team now uses the same weekly rhythm on other projects.

02 · Project Stories15 July 2026

Managing logistics on constrained urban projects

Building canal-side homes in Leiden with no storage space, narrow streets and neighbours on every side.

Grachtzijde Residences, brick apartment buildings along a canal in Leiden.
Location
Leiden
Sector
Residential
Completed
2014
View project
  1. 01Challenge

    Grachtzijde Residences sits along a historic waterfront with narrow access streets, a busy cycle route and homes on every side. There was almost no space to store materials or turn large vehicles.

  2. 02Planning

    Before mobilisation, the team mapped every delivery route, crane position and loading zone. The programme was built around what could physically reach the site each day, not only around the order of work.

  3. 03Coordination

    Deliveries were booked in time slots outside school and rush hours, and suppliers prefabricated as much as possible off site. Neighbours received regular updates on noise, closures and key activities.

  4. 04Delivery

    Materials arrived just in time and were lifted directly into place. A small daily coordination meeting kept trades, deliveries and the crane schedule aligned.

  5. 05Outcome

    The homes were completed with the street open throughout construction. The logistics approach became the starting point for other inner-city projects.

03 · Project Stories10 June 2026

From early planning through final handover

How one project team stayed with Hofkwartier Apartments from the first feasibility study to the last set of keys.

Hofkwartier Apartments, a corner apartment block in warm red brick with deep balconies in Haarlem.
Location
Haarlem
Sector
Residential
Completed
2018
View project
  1. 01Challenge

    A corner apartment block for starters and families, with a fixed budget and a clear opening date. Decisions made early would determine cost and quality right through to handover.

  2. 02Planning

    The same core team led feasibility, design coordination and construction planning. Cost estimates, buildability reviews and a realistic programme were in place before the design was finalised.

  3. 03Coordination

    Design and site experience were combined throughout. Site managers joined design meetings, and handover requirements such as documentation and inspection plans were agreed at the start.

  4. 04Delivery

    Construction followed the agreed sequence, with quality checks at each stage before work was covered up. Commissioning and inspections were planned into the programme rather than squeezed in at the end.

  5. 05Outcome

    Homes were handed over in phases with complete documentation, and the aftercare team took over a project it already knew. Keeping one team from start to finish meant fewer handovers of information and fewer surprises.

Common threads

What these projects have in common.