Practical knowledge from our project and site teams on planning, buildability and coordination.
01
2 October 2026
Why buildability reviews matter before construction begins
A design can be correct and still be difficult to build. Reviewing it with site experience early is one of the cheapest ways to avoid delays.
A buildability review asks a simple question of every part of the design: can this be built safely, in this order, with these materials and on this site? Drawings can be technically correct and still create problems once crews, cranes and weather are involved.
Typical findings are small but costly when discovered late: connections that cannot be reached for installation, elements too heavy for the planned crane, finishes that need protection for months, or details that require several trades to return to the same spot.
The value lies in timing. Changes made while the design is still on paper cost hours. The same changes made on site cost days of rework, extra materials and knock-on delays for every trade that follows.
Key points
Review the design with the people who will build it, before drawings are fixed.
Check access, lifting, sequencing and protection, not only technical correctness.
Changes on paper cost hours; the same changes on site cost days.
02
27 August 2026
What pre-construction planning should resolve early
The questions that shape cost and programme most are best answered before anyone sets foot on site.
Pre-construction is where most of a project's cost and risk is fixed. By the time work starts, the budget, programme and construction method should rest on decisions rather than assumptions.
In practice that means resolving a handful of questions early: ground conditions and foundations, the main structural approach, access and logistics, long-lead materials, permits and the sequence in which the building will be put together.
A good pre-construction phase ends with a realistic budget, a programme that site teams recognise, a clear list of remaining risks and an agreed plan for who resolves each of them.
Key points
Resolve ground conditions, structure, access and long-lead items first.
Base the programme on decisions, not assumptions.
End the phase with a clear risk list and an owner for each risk.
03
23 July 2026
How site logistics affect programme and safety
Routes, lifting zones and delivery slots decide how smoothly a site runs, and how safely.
Every site has physical limits: the space for storage, the reach of the crane, the width of the access road and the hours deliveries are allowed. A programme that ignores those limits will not hold, however carefully it is sequenced.
Good logistics planning separates people and machines, keeps walking routes clear and avoids materials being handled more than necessary. Fewer lifts and fewer movements mean less waiting and fewer moments where things can go wrong.
Logistics plans need updating as the building grows. A layout that works for the foundations rarely suits the facade or interior phase, so the plan is reviewed at every major stage.
Key points
Plan the programme around what the site can physically handle each day.
Separate people and machines, and keep walking routes clear.
Review the logistics plan at every major construction stage.
04
24 June 2026
Why technical coordination reduces rework
Most rework starts as an information problem, long before it becomes a site problem.
When architectural, structural and installation designs are developed separately, the conflicts between them only appear when someone tries to build both in the same place. On site, the fix is usually cutting, rerouting or rebuilding.
Technical coordination brings those designs together early, in one model and around one table. Clashes are checked regularly, decisions are recorded, and the drawings that reach site reflect the same agreed solution.
The result is not only less rework. Site teams spend less time waiting for answers, trades can follow each other without interruptions, and quality is easier to control when the work is built as drawn.
Key points
Combine all disciplines in one model early in the design.
Check for clashes regularly and record every decision.
Send only coordinated drawings to site.
Glossary
Terms we use.
Buildability
How easily, safely and efficiently a design can be built on a specific site.
Programme
The construction schedule: the sequence and timing of all activities.
Clash detection
Checking a combined model for places where elements from different disciplines conflict.
Work package
A defined part of the works, such as the facade or groundworks, tendered and planned as one unit.
Snagging
Recording and fixing small defects before handover.
Commissioning
Testing and adjusting installations so they work as designed before handover.