Industrial
Industrial
Polderhub Fulfilment Centre
A highly automated fulfilment centre with a full-height glazed entrance, set in the polder beside a canal, cycle path and wind turbines.
- Completed
- 2023
- Investment
- €96 million
- Location
- Lelystad
- Floor area
- 48,000 m²
- Sector
- Industrial
- Scope
- Design & Build
Project overview
Construction time
22 months
Polderhub is a 48,000 m² fulfilment centre with a high-bay automated warehouse, a full-height glazed entrance hall and dozens of loading docks. It sits in the polder beside a canal, cycle path and wind turbines that supply part of its power.
Our approach
Building on soft polder ground meant thousands of foundation piles and careful settlement monitoring. The automation supplier installed its systems while we finished the building around them, saving months on the programme.
Highlights
- 01High-bay automated warehouse
- 02Thousands of foundation piles in soft polder ground
- 03Part-powered by nearby wind turbines