Project update14 October 2026
Structural works reach completion on waterfront workplace project
The project has reached a major construction milestone as the primary structural works are completed and the next phase moves toward facade, technical installation and interior delivery.
.png&w=3840&q=75&dpl=dpl_7rr3BhjBEKFkoyAxkZ4xxsUqRK6k)
The concrete frame of the waterfront workplace project is complete. The final floor slab and roof structure were poured last month, and the structural engineer has signed off the last inspections of the frame.
Completing the structure on programme was largely a matter of sequencing. Floors were cast in a repeating cycle, so formwork, reinforcement and concrete crews could move from one section to the next without waiting for each other, and the tower crane was planned around that rhythm.
With the frame finished, the focus moves to the building envelope. Facade installation starts on the lower floors while the upper floors are made watertight, so that technical installations and interior works can begin as early as possible in a dry building.
Mechanical and electrical teams are already working from the coordinated model to install main risers and plant areas. The next milestone is a closed, weathertight building, after which the project moves into interior delivery and commissioning.